Susquehanna pipe repair: a dated worked example
Download dated susquehanna worked example (PDF)
SP330027Q0002 · Defense Logistics Agency · New Cumberland, Pennsylvania. Read the method and delivery conditions before considering a price.
Read the service beyond the code
Approximately 170 feet of 4-inch carbon-steel condensate pipe: cleaning, lining, curing and inspection. Cured-in-place pipe (CIPP) is the proposed lining method, not a generic replacement scope. Industry code 811310/product or service code K047 is outside the shared 238220 history.
Dated source: SOW p. 1 (dimensions), pp. 2-3 (method); RFQ p. 3 (NAICS/PSC); Q&A (carbon steel).
Check the company and the actual delivery team
Confirm the actual business evidence, equipment, crew and applicable conditions. Relevant history can include commercial or other reliable evidence. This RFQ generally permits unknown acceptable treatment where relevant past performance is absent; that does not waive technical capability, responsibility, eligibility or other requirements.
Dated source: RFQ p. 12.
Prove the method
Trace lining preparation, material/cure specifications, inspection and restoration to the stated requirements. Confirm compatibility and the ability to deliver; a catalog or material price alone does not establish a compliant installed repair.
Dated source: SOW pp. 2-3.
Keep the schedule conflict unresolved
The RFQ states 15 Nov 2026 completion; the SOW states 30 calendar days from official notice to proceed, or a mutually agreed final schedule. Obtain written contracting-officer clarification before committing crew time or price. Do not silently choose a controlling schedule.
Dated source: RFQ p. 4; SOW p. 4.
Separate submittals, installation and acceptance
Material data and resin cure specifications are due 5 business days before mobilization. Inspection video is due within 3 business days after curing completion. Final acceptance is separate from finishing installation. Business days and calendar days are distinct.
Dated source: SOW pp. 3-4.
Price the complete repair
Include preparation, labor, materials/resin, equipment, curing, waste and inspection; verify government-furnished responsibilities and the applicable incorporated wage determination. The 30-calendar-day firm quote hold begins from the specified quote-receipt date; it is not the performance duration.
Dated source: RFQ p. 3 (wage determination), p. 11 (quote hold); SOW pp. 2-4.
Read the evaluation condition
The dated request uses lowest overall price among responsible quoters conforming to the requirements, on an all-or-none basis; the government may reject all quotes. The absent-history alternative is one criterion, not an award guarantee.
Dated source: RFQ p. 12.
Plan acceptance, invoicing and cash
Use required receiving/supporting records and the Wide Area Workflow (WAWF) invoice route. Apply the controlling payment clauses to a cash plan; no advance-payment or unconditional payment date is promised. Clarify controlled-information designation and approved handling before any real submission.
Dated source: RFQ p. 5 and pp. 8-10 (payment/WAWF); pp. 11-12 (information handling).
Make the next move explainable
Use the worksheet and matrix to place each requirement beside company evidence and unresolved questions. Keep the schedule conflict open until written clarification. A verified specialist fills a real gap only when responsibilities and terms are agreed. No case-specific recommendation, eligibility finding or award is invented here.